Free PMP® Reference

The 12 PMP® formulas you must know for the exam

Earned Value, forecasting, PERT, communication channels, and EMV — every formula on the PMP® exam, with purpose and when-to-use notes. Bookmark this page or print it.

Most of the calculation questions on the PMP® exam fall into one of three buckets: Earned Value Management (EVM), forecasting, and a handful of one-off formulas like PERT and communication channels. The exam tests three things for each formula: what it’s for, how to calculate it, and when to apply it. Skim this reference, then drill the formulas you’re weakest on.

Earned Value

Cost Variance (CV)

CV = EV − AC
Purpose:
Measures whether the project is over or under budget at a point in time.
When to use:
Positive = under budget. Negative = over budget. Always pair with SV for full picture.

Schedule Variance (SV)

SV = EV − PV
Purpose:
Measures whether the project is ahead of or behind schedule.
When to use:
Positive = ahead of schedule. Negative = behind schedule.

Cost Performance Index (CPI)

CPI = EV ÷ AC
Purpose:
Efficiency of cost utilization — how much value you got per dollar spent.
When to use:
> 1.0 = under budget. < 1.0 = over budget. Most-tested EVM formula on the exam.

Schedule Performance Index (SPI)

SPI = EV ÷ PV
Purpose:
Efficiency of time utilization.
When to use:
> 1.0 = ahead of schedule. < 1.0 = behind schedule.

Forecasting

Estimate at Completion (EAC) — typical

EAC = BAC ÷ CPI
Purpose:
Forecasts total cost assuming current cost performance continues.
When to use:
Use when current variances are typical of future work.

Estimate at Completion (EAC) — atypical

EAC = AC + (BAC − EV)
Purpose:
Forecasts total cost assuming remaining work is on plan.
When to use:
Use when the variance was a one-time event and won’t repeat.

Estimate to Complete (ETC)

ETC = EAC − AC
Purpose:
Money still needed to finish the project from this point forward.
When to use:
Always derive from your chosen EAC method.

Variance at Completion (VAC)

VAC = BAC − EAC
Purpose:
Projected total budget surplus or shortfall at project end.
When to use:
Positive = under budget at completion. Negative = over budget.

To-Complete Performance Index (TCPI)

TCPI = (BAC − EV) ÷ (BAC − AC)
Purpose:
Cost performance required on remaining work to hit the original budget.
When to use:
If TCPI > 1.0, the team must work more efficiently than planned to recover.

Estimating

PERT (Three-Point) Estimate

PERT = (O + 4M + P) ÷ 6
Purpose:
Weighted-average estimate using optimistic, most-likely, and pessimistic values.
When to use:
Use for activities with high uncertainty. Standard deviation = (P − O) ÷ 6.

Communications

Communication Channels

n × (n − 1) ÷ 2
Purpose:
Counts the number of two-way communication channels in a project team.
When to use:
Almost guaranteed to appear on the exam. n = number of stakeholders.

Risk

Expected Monetary Value (EMV)

EMV = Probability × Impact
Purpose:
Quantifies the expected financial outcome of a risk.
When to use:
Sum EMVs across a decision branch to compare alternatives in decision trees.

How to memorize these for exam day

  1. Learn EVM first. CV, SV, CPI, SPI, and EAC together account for the majority of calculation questions. Master these and you’ve covered the bulk of exam math.
  2. Drill communication channels until it’s automatic. The n × (n−1) ÷ 2 question shows up on nearly every PMP® exam.
  3. Practice spotting which EAC variant to use. Wording like “assuming current performance continues” signals BAC ÷ CPI, while “one-time event” signals AC + (BAC − EV).
  4. Build a one-page brain dump. On exam day, immediately write all 12 formulas on your scratch paper before answering any questions. This frees your working memory.

Related resources

Stay in the loop

PMP® tips, exam updates, and study resources — straight to your inbox.

Monthly newsletter from Wiser Generations™. No spam. Unsubscribe anytime.